In a network planning scenario for remodeling a restaurant, what is the expected completion time for activity G?

Prepare for the PHFO Quantitative Analysis For Business Exam. Study with flashcards, multiple choice questions, hints, and explanations to ensure confidence and success in your exam!

Multiple Choice

In a network planning scenario for remodeling a restaurant, what is the expected completion time for activity G?

Explanation:
Estimating an activity’s duration in a network plan when there’s uncertainty is often done with the PERT approach. In PERT you use three time estimates for an activity: optimistic (best-case), most likely (typical), and pessimistic (worst-case). The expected duration is TE = (a + 4m + b) / 6, where a is the optimistic time, m is the most likely, and b is the pessimistic. The activity’s completion time on the project schedule is the earliest start time from its predecessors plus this TE. Seeing a value of 9.5 minutes as the expected time means the three estimates for activity G were combined through that PERT formula to land on 9.5. For example, with optimistic 8.5, most likely 9.5, and pessimistic 10.5, TE = (8.5 + 4×9.5 + 10.5) / 6 = 57 / 6 = 9.5 minutes. In other words, the 9.5 minutes reflects the weighted average that accounts for uncertainty, rather than a simple average or a single point estimate.

Estimating an activity’s duration in a network plan when there’s uncertainty is often done with the PERT approach. In PERT you use three time estimates for an activity: optimistic (best-case), most likely (typical), and pessimistic (worst-case). The expected duration is TE = (a + 4m + b) / 6, where a is the optimistic time, m is the most likely, and b is the pessimistic. The activity’s completion time on the project schedule is the earliest start time from its predecessors plus this TE.

Seeing a value of 9.5 minutes as the expected time means the three estimates for activity G were combined through that PERT formula to land on 9.5. For example, with optimistic 8.5, most likely 9.5, and pessimistic 10.5, TE = (8.5 + 4×9.5 + 10.5) / 6 = 57 / 6 = 9.5 minutes. In other words, the 9.5 minutes reflects the weighted average that accounts for uncertainty, rather than a simple average or a single point estimate.