In a project network, which sequence of activities forms the critical path?

Prepare for the PHFO Quantitative Analysis For Business Exam. Study with flashcards, multiple choice questions, hints, and explanations to ensure confidence and success in your exam!

Multiple Choice

In a project network, which sequence of activities forms the critical path?

Explanation:
The sequence being tested is the one that forms the longest total duration from start to finish and has zero total slack. This path determines the minimum time needed to complete the project, so any delay on it directly delays the entire project. In this network, the route through F, G, J, and K adds up to the greatest amount of work between start and finish and has no slack, which is why it is the critical path. The other routes have some slack, meaning they can be delayed a bit without extending the project’s finish date. Therefore, the F–G–J–K sequence is the critical path because it controls the project’s completion time.

The sequence being tested is the one that forms the longest total duration from start to finish and has zero total slack. This path determines the minimum time needed to complete the project, so any delay on it directly delays the entire project.

In this network, the route through F, G, J, and K adds up to the greatest amount of work between start and finish and has no slack, which is why it is the critical path. The other routes have some slack, meaning they can be delayed a bit without extending the project’s finish date. Therefore, the F–G–J–K sequence is the critical path because it controls the project’s completion time.

Subscribe

Get the latest from Passetra

You can unsubscribe at any time. Read our privacy policy