In the hospital project network, which activity has immediate predecessors C and F?

Prepare for the PHFO Quantitative Analysis For Business Exam. Study with flashcards, multiple choice questions, hints, and explanations to ensure confidence and success in your exam!

Multiple Choice

In the hospital project network, which activity has immediate predecessors C and F?

Explanation:
In a project network, an activity can start only after all of its immediate predecessors are finished. If an activity has C and F as its immediate predecessors, it must wait for both C and F to complete, and its earliest start time is the later of the two finish times. In the hospital network, the activity that begins only after both C and F are finished is the one that depends on both of them. That is why this is the correct choice—the activity that has C and F as its immediate predecessors. Other activities would have either only one of those predecessors or different prerequisites, so they wouldn’t meet the requirement of having both C and F as immediate predecessors.

In a project network, an activity can start only after all of its immediate predecessors are finished. If an activity has C and F as its immediate predecessors, it must wait for both C and F to complete, and its earliest start time is the later of the two finish times.

In the hospital network, the activity that begins only after both C and F are finished is the one that depends on both of them. That is why this is the correct choice—the activity that has C and F as its immediate predecessors. Other activities would have either only one of those predecessors or different prerequisites, so they wouldn’t meet the requirement of having both C and F as immediate predecessors.